Twelve Apostles Pipeline Project

Schedule of works and timeline

Two 11-kilometre pipelines will connect the Twelve Apostles Visitor Centre to Port Campbell to improve environmental safeguards and improve visitor experience as visitation to the site continues to grow.

One pipeline will provide a link to carry sewage from the Visitor Centre toilets to the Port Campbell Sewage Treatment Plant, ensuring Environmental Protection Authority standards are met as visitor numbers continue to rise.

An additional pipeline will be installed alongside, supplying drinkable water to the visitor centre. Currently water is trucked in daily, and the pipeline will remove over 500 trips every year.

Duration and key dates

Works commence: September 2019

Works complete: mid 2020

Works along the Great Ocean Road are now complete.
Works connecting the pipeline to the nodes at the Twelve Apostles Visitor Centre and the Port Campbell Treatment Plant will commence in February 2020.

Project funding

$8.6 million

Project information 

  • Using directional boring technology, the pipeline will be installed along the shoulder of the Great Ocean Road, minimising environmental impact and minimising vegetation removal in the road reserve and Port Campbell National Park during construction
  • Observe onsite signage directing different sized vehicles to specific parking areas.

 

X
By using our site you accept that we use and share cookies and similar technologies with certain approved third parties. These tools enable us to improve your website experience and to provide content and ads tailored to your interests. By continuing to use our site you consent to this. Please see our Privacy Policy for more information.